INDEPENDENT LOCAL NEWSNewport News, Virginia
Back to the record

Document text · Page 52 of 88

Marshall Courts Phase VII demolition — September 2024 invitation for bids

Text from the approved public copy. Page numbers follow the PDF sequence.

Open Source Document

This page was read by OCR. Text can misread numbers, dates or table columns. Check the PDF before quoting or interpreting it. Redacted areas remain redacted.

Instructions for Preparation of form HUD-51000 1. A separate breakdown is required for each project and prime contract instructions for preparation are given below. a. Heading. Enter all identifying information required for both forms. b. Columns 1 and 2. In column 4, enter the item numbers starting with No. 1, and in column 2 enter each principal division of work incorporated in the contract work. (1} Master List. The Master list contains the basic items into which any consiruction contract may be subdivided for the purpose of preparing the Construction Progress Schedule and the Periodical Estimates for Partial Payments. Only those items shall be selected which apply to the particular contract. To ensure uniformity, no change shall be made in the item numbers. Generally, about 25 to 40 major items appear in a contract. (2) Items Subdivided. In the Contractor's breakdown, against which all periodical estimates will be checked prior to pay- ment, each major item must be subdivided into sub-items pertinent to the project involved and in agreement with the Contractor's intended basis for requesting monthly pay- menis. c. Column 3. Enter the total quantity for each sub-item of each principal division of work listed in the breakdown. d. Column 4, Enter the appropriate unit of measure for each sub- item of work opposite the quantities described in column 3, such as “sq. ft.,” “cu. yd.,” “tons,” “Ib.,” “lumber per M/BM,” “brickwork per M,” etc., applicable to the particular sub-item. Items shown on “lump sum” or equivalent basis will be paid for only on completion of the whole item and not on a percentage of completion basis. e. Column 5. Enter ihe unit price, in place, of each sub-item of work, f. Column 6. Enter the amount of each sub-item obtained by multiplying the quantities in column 3 by the corresponding unit prices in column 5. g. Column 7. Enter the amount of principal item only, obtained by adding the amounts of all sub-items of each principal division of work listed in column 6. Continue with the breakdown on form HUD-51000. h. The “Schedule of Amounts for Contract Payments” shall be signed and dated in the space provided at the bottom of each sheet of the form by the individual who prepared the breakdown for the Contractor. . The minimum number of copies required for each submission for approval is an original and two copies. When approved, one fully approved copy will be returned to the Contractor. Master List of Items litem No. Division of Work Item No. Division of Work Item No. Division of Work 1 Bond 20 Rough Carpentry Site Improvements 3 General Conditions at Meta! Bucks “4 gelaining Walls Demolition & Cleari 2 aulking 5 iorm Sewers emomon earing 23 Weathersiripping 46 Sanitary Sewers Structures 24 Lath & Plastering-Drywall 47 Waier Disiribution System 4 j 25 Stucco 48 Gas Distribution System General Excavation ne 4 etribs a? 5 Footing Excavation 26 Finish Carpentry 498 — Electrical Distrioution System 6 Backfill 27 Finish Hardware 50 Street & Yard Lighting 7 Foundation Piles & Caissons 28 = Glass & Glazing 51 Fire & Police Alarm System 8 Concrete Foundations 29 Metal Doors 52 Fire Protection System 9 Concrete Superstructures 30 Metal Base & Trim §3 Street Work 10 Reinforcing Steel 31 Toilet Partitions 54 Yard Work 11 Waterproofing & Dampproofing 32 Floors . 55 (Other) 12 Spandrel Waterproofing 33 Painting & Decorating 56 = (Other) 13 34 Screens Structural Steel n . 14 Masonry 35 Plumbing Equipment 15 Stonework 36 Heating 57 Shades & Drapery Rods 18 Miscellaneous & Ornamental Metal 37 Ventilating System 58 — Ranges 17 Metal Windows 38 Elecirical 59 Refrigerators 18 Roofing 39 Elevators 60 Kitchen Cabinets & Work Tables 19 Sheet Metal 40 Elevator Enclosures—Metal 61 Laundry Equipment At Incinerators—Masonry & Paris 62 (Other) 42 (Other) 43 (Other) 63 Punch List 2 64 Lawns & Planting 1 General Conditions should be 3% to 5% of contract amount. 2 Punch List should be approximately 1/2 of 1% or $30 per dwelling unit, whichever is greater. form HUD-51006 (4/20) ref Capital Fund Guidebook Previous editions are obsolete
Jump to an indexed page (88 of 88)

Report a privacy or text-extraction issue through publication requests.