This page was read by OCR. Text can misread numbers, dates or table columns. Check the PDF before quoting or interpreting it. Redacted areas remain redacted.
CAPITAL ACTIVITY
Marshall Courts — Phase Vil Demolition of 88 Units
During the week of July 7, 2025, site preparation for the demolition project for Marshall
Courts began. Preparation is ongoing with the installation of security fencing, silt fencing and
the mobilization of equipment for the project. All permitting has been issued to the general
contractor and the anticipated start of the demolition is the week of August, 18, 2025.
Orcutt Townhomes |
The construction phase of the Orcutt Townhomes | RAD project is complete. NNRHA is
preparing for the final closing of the project that is scheduled for September 30, 2025.
Aqueduct n
The capital improvements plan for Aqueduct Apartments in currently being evaluated to
prioritize needed improvements.
Marshall Courts Apartments Phase |
Phase | of the Marshall Courts Apartments exterior renovation project is complete.
Exterior improvements include new cement board siding, exterior trim, and painting.
Electrical upgrades, roof repairs and pavement improvements were also addressed.
A ments Phase II
NNRHA staff is preparing for Marshall Courts Apartments Phase I! exterior renovations.
The in-house cost estimate has been completed. Our Procurement Department is
preparing a bid package for contractor solicitation.
Southeastern Family Project (2351 Terminal Ave.
This project is nearing completion. Final punch list items are being addressed and the
Hampton Newport News Community Services Board will reoccupy the building later this
month.
Ashe Manor
The Ashe Manor kitchen renovation project is 50% complete. Twenty-five (25) resident
kitchens have been replaced to date. The anticipated completion date for the project is
September 2025. A capital improvements plan meeting was held on Tuesday, August 5,
2025, to discuss additional capital improvement needs for Ashe Manor.
Pinecroft Apartments
Planned improvements for Pinecroft Apartments include evaluating the need to upgrade one
(1) elevator, six (6) water chiller pumps, two (2) boilers, two (2) water cooling equipment
platforms, replace water shut-off valves in all apartments that have not been replaced to
date, replace VCT tiles that are missing or damaged in common areas and elevators, paint
walls in common areas on the ‘st floor, repair or replace building entrance doors, replace
thermostats, and investigate building ground wiring issues.
1Jump to an indexed page (54 of 54)