CAPITAL ACTIVITY Marshall Courts — Phase Vil Demolition of 88 Units During the week of July 7, 2025, site preparation for the demolition project for Marshall Courts began. Preparation is ongoing with the installation of security fencing, silt fencing and the mobilization of equipment for the project. All permitting has been issued to the general contractor and the anticipated start of the demolition is the week of August, 18, 2025. Orcutt Townhomes | The construction phase of the Orcutt Townhomes | RAD project is complete. NNRHA is preparing for the final closing of the project that is scheduled for September 30, 2025. Aqueduct n The capital improvements plan for Aqueduct Apartments in currently being evaluated to prioritize needed improvements. Marshall Courts Apartments Phase | Phase | of the Marshall Courts Apartments exterior renovation project is complete. Exterior improvements include new cement board siding, exterior trim, and painting. Electrical upgrades, roof repairs and pavement improvements were also addressed. A ments Phase II NNRHA staff is preparing for Marshall Courts Apartments Phase I! exterior renovations. The in-house cost estimate has been completed. Our Procurement Department is preparing a bid package for contractor solicitation. Southeastern Family Project (2351 Terminal Ave. This project is nearing completion. Final punch list items are being addressed and the Hampton Newport News Community Services Board will reoccupy the building later this month. Ashe Manor The Ashe Manor kitchen renovation project is 50% complete. Twenty-five (25) resident kitchens have been replaced to date. The anticipated completion date for the project is September 2025. A capital improvements plan meeting was held on Tuesday, August 5, 2025, to discuss additional capital improvement needs for Ashe Manor. Pinecroft Apartments Planned improvements for Pinecroft Apartments include evaluating the need to upgrade one (1) elevator, six (6) water chiller pumps, two (2) boilers, two (2) water cooling equipment platforms, replace water shut-off valves in all apartments that have not been replaced to date, replace VCT tiles that are missing or damaged in common areas and elevators, paint walls in common areas on the ‘st floor, repair or replace building entrance doors, replace thermostats, and investigate building ground wiring issues. 1
Jump to an indexed page (54 of 54)

Report a privacy or text-extraction issue through publication requests.