Newport News Chesapeake Bay TMDL Action Plan — 2024–2029 MS4 permit

Text from the approved public copy. Page numbers follow the PDF sequence.

Open Source Document

This page uses extracted PDF text. Text can misread numbers, dates or table columns. Check the PDF before quoting or interpreting it. Redacted areas remain redacted.

City of Newport News Chesapeake Bay TMDL Action Plan (2024-2029 MS4 Permit Cycle) 3. Water Quality Projects Completed To Date Since the First Cycle MS4 Permit (2016-2021) Chesapeake Bay TMDL Action Plan, the City of Newport News has continued to construct water quality projects towards meeting TMDL requirements. Table 3-1 lists the projects and associated POC reductions that have been completed. All pollutant numbers have been updated per final as-built conditions. To date, the City has implemented projects and practices to reduce 3,411.02 pounds of Total Nitrogen per year and 1,260.60 pounds of Total Phosphorus per year. Table 3-1. Completed Water Quality Projects POC Reductions (lbs/yr) COMPLETED WATER QUALITY IMPROVEMENT PROJECTS FOR CHESAPEAKE BAY TMDL ACTION PLAN Nitrogen Phosphorus NN Police Headquarters Wet Pond 20.97 4.34 Public Works Annex Bioretention 2 2.13 0.35 Total Historical Data Reporting Credit 23.10 4.69 Hampton Avenue Channel Improvements & Constructed Wetlands (Constructed) 54.75 12.67 Public Works Operations Municipal Yard (Constructed) 8.01 0.62 Stoney Run Regional BMP (Constructed) 2,770.12 982 Total Retrofitting on Prior Developed Lands (2016-2021) 2,832.88 995.29 Glen Allen Court Channel Improvements (Constructed) 78.75 71.4 Turnberry Channel Improvements (Constructed) 49.39 52.61 Total First Cycle Stormwater Management Projects (2016-2021) 128.14 124.01 Lynchburg Drive Channel Improvements (Constructed) 54.23 49.16 Richneck Area Regional Water Quality & Flood Control BMP (Constructed) 135.40 28.39 Thalia / Saddler Drives Channel Improvements (Constructed) 65.1 59.02 Completed Stormwater Management Projects (2022-2024) 254.73 136.57 Lee Hall Well 1 NMP 0.19 0.007 Lee Hall Well 2 NMP 0.144 0.005 Skiffes' Creek Pump Station NMP 0.118 0.004 Jefferson Avenue Pump Station NMP 0.22 0.024 Total Urban Nutrient Management Plans 0.672 0.04 2022-2024 Septic Disconnects (49 total residences) 171.5 0.00 Total Nutrient Reductions To Date 3,411.02 1,260.60 4. Planned Water Quality Projects for 2024-2029 Permit Cycle The following projects and nutrient credit purchases are planned for the 2024-2029 MS4 Permit cycle to meet the current MS4 Permit TMDL requirements. 5
Jump to an indexed page (31 of 31)

Report a privacy or text-extraction issue through publication requests.