City of Newport News
Chesapeake Bay TMDL Action Plan
(2024-2029 MS4 Permit Cycle)
Governor Drive Stream Restoration and Constructed Wetland BMP
The Governor Drive Stream Restoration and Constructed Wetland BMP includes approximately 885 linear
feet of stream restoration and a Level 1 constructed wetland. The contributing drainage area is
approximately 102.2 acres (43% impervious), and this project will generate approximately 57.87 pounds
of phosphorus reduction credit. Construction began in December 2025 and is expected to be completed
by summer 2025 for an estimated $2,857,736 or $49,382 per pound TP removed. Grant funding has been
awarded through DEQ SLAF. Drainage areas and POC reduction credits were generated by the design
engineers. Pollutant numbers will be updated per final as-built conditions.
Stream Restoration &
Project Type Constructed Wetland BMP
Total Area Treated (ac) 102.2
Impervious Area (%) 43%
N Reduction (lb/yr) 212.00
P Reduction (lb/yr) 57.87
Estimated Cost for
Construction $2,857,736