NNRHA April 15, 2025 board meeting package

Text from the approved public copy. Page numbers follow the PDF sequence.

Open Source Document

This page was read by OCR. Text can misread numbers, dates or table columns. Check the PDF before quoting or interpreting it. Redacted areas remain redacted.

CAPITAL ACTIVITY Marshall Courts — Phase VII Demolition of 88 Units All residents have been relocated from the 88 apartments in the demolition phase of Marshall Courts and the utilities to the site have been terminated C.M. Munden, the general contractor for the project, has mobilized and is preparing to start demolition. The project is scheduled to be completed in November 2025. Orcutt Townhomes | Three of the six accessible lift systems for Orcutt Townhomes | have been installed. The remaining | lifts are scheduled to be installed in May 2025. After the lift installations are complete, the City and VHDA will conduct final inspections of those units. Aqueduct Apartments The repaving project for Aqueduct Apartments started on March 30, 2025. It is being performed in several phases. The project is scheduled to be completed in 30 days. DJG Architects have provided the specifications and scope of work for the window replacement project. NNRHA staff is currently reviewing the information and we anticipate work will begin this summer. Marshall Courts Apartments A pre-construction meeting was held for the exterior renovations project for Marshall Courts Phase | | on Thursday, April 3, 2025. The project is scheduled to start during the week of April 7th, 2025. There is a 6-month timeframe to complete the project. Southeastern Family Project (2351 Terminal Ave.) The project is currently 65% complete. Windows and doors are scheduled for installation soon and interior finish work will begin shortly thereafter. The project is scheduled for completion in May. Ashe Manor Cabinet submittals have been reviewed and approved by the project architect. All materials will be stored onsite to expedite the project timeline. We anticipate completing this project in 7 months without relocating the residents. Pinecroft Apartments DJG Architects has completed the specifications and scope of work for capital improvements needed at Pinecroft Apartments. Upon completion of review and approval by NNRHA staff, NNRHA | procurement will initiate contractor solicitation for the project. |
Jump to an indexed page (43 of 43)

Report a privacy or text-extraction issue through publication requests.