This page was read by OCR. Text can misread numbers, dates or table columns. Check the PDF before quoting or interpreting it. Redacted areas remain redacted.
CAPITAL ACTIVITY
Marshall Courts — Phase VII Demolition of 88 Units
All residents have been relocated from the 88 apartments in the demolition phase of Marshall
Courts and the utilities to the site have been terminated C.M. Munden, the general contractor for the
project, has mobilized and is preparing to start demolition. The project is scheduled to be completed
in November 2025.
Orcutt Townhomes |
Three of the six accessible lift systems for Orcutt Townhomes | have been installed. The remaining |
lifts are scheduled to be installed in May 2025. After the lift installations are complete, the City and
VHDA will conduct final inspections of those units.
Aqueduct Apartments
The repaving project for Aqueduct Apartments started on March 30, 2025. It is being performed in
several phases. The project is scheduled to be completed in 30 days.
DJG Architects have provided the specifications and scope of work for the window replacement
project. NNRHA staff is currently reviewing the information and we anticipate work will begin this
summer.
Marshall Courts Apartments
A pre-construction meeting was held for the exterior renovations project for Marshall Courts Phase | |
on Thursday, April 3, 2025. The project is scheduled to start during the week of April 7th, 2025.
There is a 6-month timeframe to complete the project.
Southeastern Family Project (2351 Terminal Ave.)
The project is currently 65% complete. Windows and doors are scheduled for installation soon and
interior finish work will begin shortly thereafter. The project is scheduled for completion in May.
Ashe Manor
Cabinet submittals have been reviewed and approved by the project architect. All materials will be
stored onsite to expedite the project timeline. We anticipate completing this project in 7 months
without relocating the residents.
Pinecroft Apartments
DJG Architects has completed the specifications and scope of work for capital improvements
needed at Pinecroft Apartments. Upon completion of review and approval by NNRHA staff, NNRHA |
procurement will initiate contractor solicitation for the project. |Jump to an indexed page (43 of 43)