Newport News Repetitive Loss Plan Progress Report
Action Action Location Funding Lead Priority Deadline Status
Type Source
Christopher Shores Warwick: Local Engineering Medium 2024 Design is
Drainage Christopher Stormwater Department complete
Improvements. Shores Fees, CIP and
Address repeated subdivision construction
flooding in the is underway
Christopher Shores
subdivision by
installing larger
storm pipes and
additional pipes
and inlets to
alleviate flooding
during tidal events.
(Design almost
complete)
Hilton South Hilton/Brandon CIP Engineering Medium 2027 Ongoing
Drainage Heights Department
Improvements.
Install a new
system, designed to
current standards,
within the City’s
right-of-way
James River Hilton/Brandon CIP, Local Engineering Medium 2024 Design is
Shoreline Heights: James Stormwater Department complete
Stabilization. River along Fees
Stabilize 720 linear River Rd from
feet of shoreline on 9304 to 9508
the James River to River Road
address severe
erosion and failure