Residential Rehabilitation Program
February 2026 Housing Rehabilitation Activity:
Total Housing Rehabilitation Activity for February 2026
Residential Repair Program Cases
Projects Completed
Projects in Underwriting
Projects Pending Approval
Projects Ongoing
Projects Ineligible
Total
Calendar Year 2026 (January 1, 2026 —- December 31, 2026):
New Housing Rehabilitation Applications Total New Housing Rehabilitation
for Applications Received for
January 1, 2026 - January 31, 2026 January 1, 2026 — January 31, 2026
4 1
Marshall-Ridley Residential Facade Program
A total of 163 applications for the Marshall-Ridley Residential Facade Program across two
funding rounds have been reviewed. During Round One, 113 applications were processed,
resulting in 76 completed facade improvement projects. In Round Two, 50 applications were
processed, leading to 13 completed projects to date. Program activity remains active, with
18 inspections completed, 17 applications reviewed for code compliance, 24 reviewed by
finance, 5 contracts executed, and 6 contracts currently pending execution. Eleven (11)
applications in this round were deemed ineligible. No applications in either round require
administrative review, allowing staff to maintain efficient processing timelines. To date, the
program has expended $1,735,239.02 of the $2.1M granted by the City of Newport News,
with $357,835.98 remaining to support continued fagade improvements within the Marshall-
Ridley community.
Marshall-Ridley Residential Facade Program Activity Tracker
First Round — Completed | Second Round
(7/21/25)
Total Applicants 113 50
Administrative Review 0
Finance Review 24
Inspected 18
Codes Review 17
Contract Pending 6
Contracted 5
Completed 18