INDEPENDENT LOCAL NEWSNewport News, Virginia
Filter results · 1 applied
Clear search

18 records

1–18 of 18

Meetings & decisionsArchived file

NNRHA Board of Commissioners regular meeting package — August 18, 2026

Other public body · Newport News Redevelopment and Housing AuthorityAugust 18, 2026

Meeting agenda and supporting material on housing grants, financing, operations and authority reports.

Source notes & file details

August 18, 2026 agenda and supporting reports; a meeting package is not standalone adopted minutes. Reviewed public copy with identifiable participant photographs withheld; program descriptions, official business and page numbering retained.

File: nnrha-board-package-2026-08-18-privacy-redacted.pdf

Meetings & decisionsArchived file

NNRHA Board of Commissioners regular meeting package — September 15, 2026

Other public body · Newport News Redevelopment and Housing AuthoritySeptember 15, 2026

Agenda, prior minutes, agency and capital plans, policy proposals, financial and inspection materials.

Source notes & file details

September 15, 2026 meeting package, including August 18 minutes and proposed agency, capital and policy items. Agenda proposals do not establish adoption. Reviewed public copy with identifiable participant photographs withheld; program descriptions, official business and page numbering retained.

File: nnrha-board-package-2026-09-15-privacy-redacted.pdf

Meetings & decisionsSource link

NNRHA December 17, 2024 board meeting package

Other public body · Newport News Redevelopment and Housing AuthorityDecember 17, 2024

Authority meeting materials reporting the award of Marshall Courts Phase VII demolition to C. M. Munden.

Source notes

Physical PDF page 53, printed page 9, reports the contractor award and an expected January 2025 start. The passage does not give the executed price or exact award date. Relevant page visually verified October 11, 2026. This is a link to the official publisher copy; the complete meeting package is not archived or text-indexed here.

Meetings & decisionsSource link

NNRHA February 18, 2025 board meeting package

Other public body · Newport News Redevelopment and Housing AuthorityFebruary 18, 2025

Authority meeting materials including the 2024 Annual Activity Report, which dates the Marshall Courts Phase VII demolition award to December 2024.

Source notes

Physical PDF page 41 of the 2024 Annual Activity Report gives the award month, not an exact date or executed price. Page 41 visually verified October 11, 2026. This is a link to the official publisher copy; the complete meeting package is not archived or text-indexed here.

OtherSource link

Marshall Courts Phase VII land-disturbance permit LD-2025-0027

City of Newport News · City of Newport NewsDate not specified

City public permit summary for Phase VII demolition, grading and green-space seeding. It records September 1, 2026 administrative finalization, which does not establish physical completion or roadway acceptance.

Source notes

Public summary checked October 11, 2026: Inactive; applied July 28, 2025; finalized September 1, 2026; parcel 300030205. Detail-page issue/expiry dates are September 2, 2025/2026; search results show September 3, 2025/2026. The discrepancy is unresolved, so no issue date is assigned here. The description cites a plan dated September 4, 2025; SITE-2023-0011 displays a September 4, 2024 processing-completion date. Those dates are not reconciled. Inspection and attachment details require record-contact access and were not reviewed. Administrative status does not establish physical completion, roadway acceptance or correction approval. Link-only source; no portal attachments are archived.

OtherSource link

Marshall Courts Phase VII right-of-way permit ROW-2025-1243

City of Newport News · City of Newport NewsDate not specified

City public permit summary for demolition of asphalt parking and sidewalk and replacement of sidewalks, curb, gutter and entrances. Its description does not expressly identify or accept the 2026 roadway correction.

Source notes

Public summary checked October 11, 2026: Issued; applied August 21, 2025; finalized date blank; expiry October 30, 2026; parcel 300030205. The detail page shows an issue date of September 2, 2025, while search results show September 3; no issue date is assigned here. The description cites a September 4, 2025 plan date, distinct from SITE-2023-0011’s displayed September 4, 2024 processing completion. The differences remain unresolved. Restricted inspection details were not reviewed. An issued status or blank finalized date does not establish current physical progress or an unfinished project. Portal fees are not a construction-cost record. Link-only source; no portal attachments are archived.

OtherSource link

Marshall Courts Phase VII site plan SITE-2023-0011

City of Newport News · City of Newport NewsDate not specified

City public Class 1 site-plan summary for demolition of residential units, green-area restoration and sidewalk work within the right of way. Plan-processing completion is distinct from construction completion.

Source notes

Public summary checked October 11, 2026: Approved; applied March 3, 2023; displayed completion September 4, 2024; parcel 300030205. This is a plan-processing date, not the document issue date, construction completion or approval of the 2026 correction. The related permit descriptions cite September 4, 2025; approved and revised drawings are needed to explain that difference. No inspection history or approved/revised drawings were obtained. Link-only public summary; no portal attachments are archived.

Meetings & decisionsArchived file

NNRHA April 15, 2025 board meeting package

Other public body · Newport News Redevelopment and Housing AuthorityApril 15, 2025

Authority meeting materials including Marshall Courts Phase VII demolition contractor and schedule reporting.

Source notes & file details

Physical PDF page 35, printed page 10, identifies C.M. Munden as general contractor. This dated report does not establish the final contract price or actual completion. Official source contents reviewed October 8, 2026.

File: nnrha-board-package-2025-04-15.pdf

Meetings & decisionsArchived file

NNRHA August 19, 2025 board meeting package

Other public body · Newport News Redevelopment and Housing AuthorityAugust 19, 2025

Authority meeting materials including the reported start of Marshall Courts Phase VII site preparation and demolition planning.

Source notes & file details

Physical PDF page 51, printed page 11. Preparation began the week of July 7 and demolition was expected the week of August 18. These are reported status and expectations. Official source contents reviewed October 8, 2026.

File: nnrha-board-package-2025-08-19.pdf

Meetings & decisionsArchived file

NNRHA December 16, 2025 board meeting package

Other public body · Newport News Redevelopment and Housing AuthorityDecember 16, 2025

Authority meeting materials including Marshall Courts Phase VII demolition progress and revised completion forecast.

Source notes & file details

Physical PDF page 59, printed page 13, reports nine of thirteen buildings demolished and an early-2026 forecast. Contractual deadlines and acceptance require separate records. Official source contents reviewed October 8, 2026.

File: nnrha-board-package-2025-12-16.pdf

Meetings & decisionsArchived file

NNRHA June 16, 2026 board meeting package

Other public body · Newport News Redevelopment and Housing AuthorityJune 16, 2026

Authority meeting materials including pouring of Marshall Courts Phase VII sidewalks, curbs and gutters and a June completion forecast.

Source notes & file details

Physical PDF page 725, printed page 3. The forecast precedes later reported drainage correction work; it does not establish acceptance or payment. Official source contents reviewed October 8, 2026.

File: nnrha-board-package-2026-06-16.pdf

Meetings & decisionsArchived file

NNRHA March 2025 Report to the Board

Other public body · Newport News Redevelopment and Housing AuthorityDate not specified

Authority report including Marshall Courts Phase VII notice-to-proceed status and a November 2025 completion forecast.

Source notes & file details

Month-only report date. Capital Activity, printed page 13. Reported forecasts should be checked against the executed contract, notice to proceed and approved extensions. Official source contents reviewed October 8, 2026.

File: nnrha-board-report-2025-03.pdf

Meetings & decisionsArchived file

NNRHA July 2026 Report to the Board — Marshall Courts drainage correction

Other public body · Newport News Redevelopment and Housing AuthorityDate not specified

Authority report describing drainage deficiencies in Marshall Courts Phase VII curbs and gutters and a proposed corrective change order involving 36th Street.

Source notes & file details

Month-only report date. Physical PDF page 5, printed page 3. The authority refers to the City highway pin and stormwater standards; the report does not settle technical responsibility or the correction price. Official source contents reviewed October 8, 2026.

File: nnrha-board-report-2026-07.pdf

Contracts & purchasingArchived file

Marshall Courts Phase VII demolition — September 2024 invitation for bids

Other public body · Newport News Redevelopment and Housing AuthoritySeptember 30, 2024

Solicitation for demolition and associated site work at Marshall Courts Phase VII. Includes blank bid and contract forms and HUD general conditions.

Source notes & file details

Physical PDF pages 4–6, 10, 68 and 74–76 contain relevant scope and administration provisions. Printed bid-number variants MCP7D-09-24 and MCDP7-09-24 should both be searched. Posted solicitation does not establish an executed price or final responsibility. Official source contents reviewed October 8, 2026.

File: nnrha-marshall-phase-vii-ifb-2024.pdf

Contracts & purchasingSource link

Marshall Courts Phase 3 facade repairs and painting — notice of award

Other public body · Newport News Redevelopment and Housing AuthoritySeptember 17, 2026

Award notice identifying Stuart's Contracting LLC as the selected contractor.

Source notes

Official notice of award dated September 17, 2026, referencing solicitation MCF3P-08-26 and recipient Stuart's Contracting LLC. The listing date is not substituted for the date on the notice. Verified October 8, 2026.

Contracts & purchasingSource link

Marshall Courts Phase 3 facade repairs and painting — NNRHA ITB MCF3P-08-26

Other public body · Newport News Redevelopment and Housing AuthorityAugust 7, 2026

Bid specifications and project requirements for the third phase of facade repairs and painting.

Source notes

Official invitation to bid issued August 7, 2026, verified on cover. Related addenda and award are separately published by NNRHA. Bid scope does not establish completion. Verified October 8, 2026.

Contracts & purchasingSource link

Marshall Courts roof overlay, fascia and gutter repair — notice of award

Other public body · Newport News Redevelopment and Housing AuthoritySeptember 28, 2026

Award notice identifying Centennial Contractors Enterprises as the selected contractor.

Source notes

Official notice of award dated September 28, 2026, referencing solicitation MCRFG-08-26 and recipient Centennial Contractors Enterprises. Award notice is not a final payment or completion record. Verified October 8, 2026.

Contracts & purchasingSource link

Marshall Courts roof overlay, fascia and gutter repair — NNRHA ITB MCRFG-08-26

Other public body · Newport News Redevelopment and Housing AuthorityAugust 14, 2026

Bid specifications and project requirements for roof overlay, fascia and gutter repairs.

Source notes

Official invitation to bid issued August 14, 2026, verified on cover. Related addendum and award are separately published by NNRHA. Bid scope does not establish completion. Verified October 8, 2026.