CAPITAL ACTIVITY
Marshall Courts — Phase VII Demolition of 88 Units
All residents have been relocated from the 88 apartments in the demolition phase of Marshall
Courts. The contractor has been given the notice to proceed and is currently preparing the site. The
project is scheduled to be completed in November 2025.
Orcutt Townhomes |
The fabrication of 6 accessible lift systems for Orcutt Townhomes | is underway. The first systems
are anticipated to be installed the week of March 10, 2025. After the lift installations are complete,
the City and VHDA will conduct final inspections of those units.
Aqueduct Apartments
The anticipated start date is March 24, 2025 for the repaving project for Aqueduct Apartments to be
completed by Centennial Contractors. This project will be performed in several phases to minimize
impact on residents. DJG Inc. Architects have completed specifications and the scope of work for
the window replacement project at Aqueduct Apartments. We anticipate that work will begin later
this spring.
Marshall Courts Apartments
Centennial Contractors is preparing to mobilize and begin exterior renovations for Marshall Courts
Phase |. All material selections have been finalized. The contractor is securing materials and
construction will begin later this month.
Southeastern Family Project (2351 Terminal Ave.)
Renovation work at the Southeastern Family Project Building is progressing well. The HVAC system
is currently being installed. Windows and cabinets will be delivered soon. The project is anticipated
to be completed by late April or early May.
Ashe Manor
The Ashe Manor kitchen cabinet replacement project was awarded to Stuart’s Contracting, LLC.
The notice to proceed was issued on February 26, 2025. Materials and supplies are in the process
of being ordered, secured, and stored. The timeline for completing this project is 210 calendar days.
Pinecroft Apartments
DJG Inc. Architects are completing specifications and the scope of work for capital improvements to
Pinecroft Apartments. NNRHA procurement staff will initiate contractor
solicitation in coming weeks.