NNRHA March 2025 Report to the Board

Text from the approved public copy. Page numbers follow the PDF sequence.

Open Source Document

This page was read by OCR. Text can misread numbers, dates or table columns. Check the PDF before quoting or interpreting it. Redacted areas remain redacted.

Contracted Completed Ineligible CAPITAL ACTIVITY Marshall Courts — Phase VII Demolition of 88 Units All residents have been relocated from the 88 apartments in the demolition phase of Marshall Courts. The contractor has been given the notice to proceed and is currently preparing the site. The project is scheduled to be completed in November 2025. Orcutt Townhomes | The fabrication of 6 accessible lift systems for Orcutt Townhomes | is underway. The first systems are anticipated to be installed the week of March 10, 2025. After the lift installations are complete, the City and VHDA will conduct final inspections of those units. Aqueduct Apartments The anticipated start date is March 24, 2025 for the repaving project for Aqueduct Apartments to be completed by Centennial Contractors. This project will be performed in several phases to minimize impact on residents. DJG Inc. Architects have completed specifications and the scope of work for the window replacement project at Aqueduct Apartments. We anticipate that work will begin later this spring. Marshall Courts Apartments Centennial Contractors is preparing to mobilize and begin exterior renovations for Marshall Courts Phase |. All material selections have been finalized. The contractor is securing materials and construction will begin later this month. Southeastern Family Project (2351 Terminal Ave.) Renovation work at the Southeastern Family Project Building is progressing well. The HVAC system is currently being installed. Windows and cabinets will be delivered soon. The project is anticipated to be completed by late April or early May. Ashe Manor The Ashe Manor kitchen cabinet replacement project was awarded to Stuart’s Contracting, LLC. The notice to proceed was issued on February 26, 2025. Materials and supplies are in the process of being ordered, secured, and stored. The timeline for completing this project is 210 calendar days. Pinecroft Apartments DJG Inc. Architects are completing specifications and the scope of work for capital improvements to Pinecroft Apartments. NNRHA procurement staff will initiate contractor solicitation in coming weeks. 13
Jump to an indexed page (19 of 19)

Report a privacy or text-extraction issue through publication requests.