August 18, 2025
From: Jacob R. (Jake) Wiseman, Dominion Energy
To / copied participants: Mallory Butler and Sameera Younus-Khan; Derek Perry and Daniel Kociola copied
Good afternoon,
It was a pleasure meeting and speaking with both of you. Regarding your inquiry about capacity availability
at 165 Yorktown Rd and 100 Dozier Rd, we recommend submitting a High-Level Feasibility Study request.
This study is offered at no cost and typically takes approximately four to six weeks to complete. It provides a
snapshot of available power from existing distribution infrastructure and outlines any potential transmission
or substation upgrades that may be necessary to support the larger power blocks commonly required by data
centers. We can also provide preliminary timelines for these components. It's important to note that most
new data center projects now require a dedicated substation.
To initiate the process, please submit your request via our Data Center Request Submission Form linked
below. I've also included additional resources that may be helpful.