Coal monitoring: DEQ explains September 2025 procurement delay

The September 7 reply contains DEQ鈥檚 September 2 explanation that construction bids were about 35% above the original 2020 costing structure and EPA review of a revised grant budget was needed before award. Its projected 30-day construction period was conditional, not evidence of installation.

Public body
City of Newport News
Department / subject
City Manager's Office / released interagency correspondence
Document date
September 2, 2025
Open Public Release Index

Record details

Page options

Document details

Record type
Public release index

Source notes

Original department / subject label: City Manager / released interagency correspondence

Targeted review of publicly released correspondence, November 14, 2026. 000000042.eml; September 7, 2025; RE: TAME Project overview and status; embedded September 2 DEQ message. Original attachment filenames recur in the release; date and subject disambiguate. No raw correspondence, private contact details or meeting credentials republished.

Report a correction, privacy, safety, or copyright concern through Contact & Corrections.