EVALUATION TABULATION
IFB No. 25-3598-6256
Lee Hall Reservoir Floating Docks Replacement
EVALUATION TABULATION
Invitation for Bids - Lee Hall Reservoir Floating Docks Replacement
Page 2
Base Bid Items
Crofton Construction
Services, Incorporated
Hodges & Hodges
Enterprises LLC
John K. George & Company Seaward Marine Corporation
Selected
Line Item
Description
Quantity
Unit of
Measure
Unit Cost
Total
Unit Cost
Total
Unit Cost
Total
Unit Cost
Total
X
4
New Floating Docks
6000
Square foot
$98.00
$588,000.00
$72.50
$435,000.00
$79.93
$479,580.00
$120.06
$720,360.00
X
5
New Piles - Floating Docks
and Approaches
1050
Linear Feet
$54.00
$56,700.00
$45.50
$47,775.00
$82.00
$86,100.00
$73.08
$76,734.00
X
6
2 Aluminum Gangways
1
Lump Sum
$57,100.00
$57,100.00
$29,530.00
$29,530.00
$31,620.00
$31,620.00
$54,430.01
$54,430.01
Total
$897,500.00
$730,205.00
$760,650.00
$1,113,490.26
ADDITIVE AND DEDUCTIVE BID ITEMS
Additive and Deductive Bid Items
Crofton Construction
Services, Incorporated
Hodges & Hodges
Enterprises LLC
John K. George & Company Seaward Marine Corporation
Selected
Line Item
Description
Quantity
Unit of
Measure
Unit Cost
Total
Unit Cost
Total
Unit Cost
Total
Unit Cost
Total
Pricing For Additive Bid Item 1
X
7
New Piles -
Fixed Pier
450
Linear Feet
$43.00
$19,350.00
$45.50
$20,475.00
$62.00
$27,900.00
$167.97
$75,586.50
X
8
New Fixed
Wooden Pier
480
Square feet
$126.00
$60,480.00
$54.00
$25,920.00
$101.65
$48,792.00
$282.94
$135,811.20
Pricing For Deductive Bid Item 2
9
Treated
Wood 2x6
Decking
Credit
1
Lump Sum
-$37,500.00
-$37,500.00
$37,586.00
$37,586.00
$37,586.00
$37,586.00
-$25,200.00
-$25,200.00
Total
$79,830.00
$46,395.00
$76,692.00
$211,397.70Jump to an indexed page (2 of 2)