Contracts & purchasingSource link
Warwick Boulevard drainage improvements: City project-status record 620
City project description, dated schedule comment, delivery milestones and displayed contract/payment figures.
Why this record matters
Dynamic City display: the capture date and dated staff comment are distinct from underlying contractual events.
The public tracker lists inspection costs beyond the construction line: Project 620 shows $8,186,170.23 paid to date on Basic’s $11,125,518.25 line. It also displays $264,846.82 for Century inspection and $5,235 for Terracon QA testing, or $270,081.82 across those two separate displayed rows. The relief guidelines cap reimbursement to an eligible business at $7,500. A complete corridor account needs the construction and support contracts, time extensions, and a separate grant ledger showing relief awarded and paid by the December application deadline.
Source notes
Dynamic official project page captured October 17, 2026. Its comment is dated February 23, 2026; capture date is not the date of every schedule or contract value. Construction, construction closeout and project closeout are separate milestones. The City includes an accuracy disclaimer. The displayed Basic contract amount is not independently verified as an original award or final cost. Source-only link; no page archive or new person profiles.