Active · Investigation · Reviewed October 18, 2026
Southeast Community Greenway planning-grant status
Newport News was selected for $1 million in federal planning funding for the Southeast Community Greenway Reconnector. The reviewed record does not establish the award's legal obligation status, remaining funding or accepted planning products.
Overview
Establish the funding and delivery record for the proposed 28th Street bridge connection between downtown and the Southeast Community. The selection was for planning, not construction of the entire project. No loss of this award, improper payment or missed binding deadline is established.
Source notes
A selection, signed agreement, obligation, reimbursement and accepted deliverable are different stages. Dashboard percentages are not completion certifications; the City itself warns that displayed information requires verification. Federal policy changes, a stale comment, partial obligation or replacement funding could change the account. Application-assistance costs do not establish duplication or waste. Responsibility for any later funding loss would require a separate documentary chronology.
Timeline
Dates follow the cited records; document dates are labeled separately.
August–October 2022 and August–October 2023
Application-assistance engagements are shown paid
The City dashboard displays two application-assistance engagements, $55,145.59 and $34,451.68, totaling $89,597.27, both shown fully paid. Contract periods are not payment dates, and the dashboard does not identify their funding source or establish federal reimbursement.
September 2023
One proposed study and alternative funding scenarios
The Council application package proposed one $1 million study with an $800,000 federal share and $200,000 City share. Application budget forms also list a $1 million NAE scenario with no local share, consistent with alternative program consideration. The rows do not establish two awards. Proposed dates of October 2024–October 2026 were application fields, not a verified binding grant deadline.
- Southeast Community Greenway: September 2023 application endorsement package · September 12, 2023 application endorsement package, summary pp. 1–2; proposed resolution p. 4.
- Southeast Community Greenway: released application documents · G015862-050126 application release: grant narrative pp. 1, 4–6, 10; budget narrative pp. 1–6; SF424/SF424A funding and dates fields.
- USDOT FY23 Reconnecting Communities and Neighborhoods funding notice · July 5, 2023 FY23 RCN funding notice, pp. 1–3, 8, 12.
March 2024
Federal planning selection and early outreach
USDOT identified a $1 million NAE planning selection for Newport News. The proposed work included traffic analysis, alternatives and preliminary design, community involvement and environmental review. The application reported 208 survey responses; those are affirmative evidence of early outreach, not proof of representative or continuing engagement.
- USDOT FY23 Reconnecting Communities and Neighborhoods awards factsheet · March 2024 awards factsheet, printed p. 133 / PDF p. 134; NAE planning selection, Newport News.
- Southeast Community Greenway: released application documents · G015862-050126 application release: grant narrative pp. 1, 4–6, 10; budget narrative pp. 1–6; SF424/SF424A funding and dates fields.
July 4, 2025
Unobligated program balances rescinded; award status unresolved
Public Law 119-21 rescinded unobligated NAE balances. The provision alone does not establish what happened to this individual selection; award-specific obligation records are needed.
March 4, 2026
Dated dashboard comment reports an unexecuted agreement
A dated City dashboard comment states, “Agreement not executed by FHWA.” It remained visible during the October 18 review. It does not by itself establish cancellation, current accuracy or the absence of a separate or partial obligation.
May 1, 2026
Application-focused records request closes
The City closed the application-focused records request as a full release. Its scope did not purport to include every later implementation record.
6 of 6 reviewed records. Source links, source collections and release indexes are identified separately from archived copies.
Source link · Date not specified
USDOT FY23 Reconnecting Communities and Neighborhoods awards factsheet
USDOT FY23 RCN Awards Factsheet, March 2024, printed p. 133 / PDF p. 134
Source link · Date not specified
Southeast Community Greenway: City project 1169 status dashboard
City project 1169, Downtown & SE Community Greenway Connector Feasibility Study, Description, Comments, Contracts, Schedule and disclaimer; reviewed October 18, 2026
Source link · September 12, 2023
Southeast Community Greenway: September 2023 application endorsement package
September 12, 2023 Council application endorsement package, summary pp. 1–2, proposed resolution p. 4
Source link · Date not specified
Southeast Community Greenway: released application documents
Request G015862-050126: “RCN_Grant_Narrative_FINAL.pdf,” pp. 1, 4–6, 10; “RCN_Grant_Budget_Narrative_FINAL.pdf,” pp. 1–6; “SF424_4_0-V4.0.pdf,” project dates and funding fields; “SF424A-V1.0.pdf,” Budget Summary and Non-Federal Resources.
Source link · July 4, 2025
Public Law 119-21: §60019 unobligated Neighborhood Access and Equity balances
Public Law 119-21, §60019, 139 Stat. 156 / PDF p. 86
Source link · July 5, 2023
USDOT FY23 Reconnecting Communities and Neighborhoods funding notice
USDOT FY23 RCN funding notice, July 5, 2023, pp. 1–3, 8 and 12, explaining alternative program consideration, agreement/obligation and match
News story
No resulting news story is currently linked and published.
Open questions
Records still needed (4)
Award obligation status
Was any award amount legally obligated, on what date and under which federal and state project identifiers?
Likely custodian: City project administration, FHWA and USDOT
Resolve this documentary question without treating an unavailable record as proof of wrongdoing.
Submit this recordAgreement and matching contribution
What signed agreement, amendments or award-specific disposition establish current availability and the actual matching contribution?
Likely custodian: City project administration, FHWA and USDOT
Resolve this documentary question without treating an unavailable record as proof of wrongdoing.
Submit this recordAccepted planning products
Which planning products were commissioned, accepted and paid for, and what work remains useful?
Likely custodian: City project administration, FHWA and USDOT
Resolve this documentary question without treating an unavailable record as proof of wrongdoing.
Submit this recordDashboard definitions and resident updates
What does the City dashboard measure, and what funding or schedule changes have been communicated to residents?
Likely custodian: City project administration, FHWA and USDOT
Resolve this documentary question without treating an unavailable record as proof of wrongdoing.
Submit this record