Habersham intersections: funding, construction and pedestrian safety

Overview

Boykin Lane was already crossed out of the May 2025 construction bid. A separate agreement assigns its pedestrian refuge to Costco. The City’s purchase order confirms $5,987,777 for Allan Myers. A separate inspection order is $2,000 below the tracker entry. Acceptance, the reason for the difference and later contractor payments remain unverified.

Background & source notes

Follow the work procured under UPC 108723, including the Habersham and Chatham intersection off Jefferson Avenue. Compare the scope advertised to bidders with final changes, acceptance and pedestrian safety results.

Source notes and limitations

The signed agreement assigns the Boykin improvement to Costco. Whether work changed hands later, whether the crossing was accepted, and what the contractor or Costco ultimately received require later signed records. The vendor register covers check dates through July 8, 2026.

Case details

Page options

Where things stand

Updated

From the reviewed timeline

The bid tabulation confirms both competing prices

August 11, 2026

The official tabulation lists Allan Myers at $5,987,777 and Parkway Grading at $6,377,798.85, a difference of $390,021.85. Procurement identifies Allan Myers as selected. Its bid, the April purchase order and the Engineering tracker agree on the amount. Actual progress payments require separate records.

View timeline entry and sources

Open question

Funding on the day of the construction order

The April 20 pre-encumbrance ledger for J3050, budget entries before and after the May 12 vote, and the June 26 purchase-order change history.

View all 6 open questions

Money Trail

No itemized funding entries are published for this case.

Evidence

Habersham purchase order and payments

The construction order identifies how the City coded $5,987,777. The vendor register separately identifies four checks to the lighting and Phase I inspection contractors.

Go to the data tables
Allan Myers purchase order 20262818
Workbook rowFundYear in account codeAmount ordered
23864300—$2,993,888.50
238841042018$1,150,428.28
239041042016$12,346.76
239241042017$442,736.77
239441042020$3,261.44
239641042022$31,029.92
239841042013$164,735.71
240041042015$43,582.62
240241042022$1,145,767.00

All nine lines identify J3050. The two 2022-coded rows are separate lines on the same order. Each fund totals $2,993,888.50. The source header records $0 liquidated and a June 26 change date.

Four project payments matched to the tracker
PayeeCheck dateCheck numberInvoice net
Virginia Electric and PowerMay 21, 2025143350$29,743.62
Virginia Electric and PowerJune 6, 2025143862$17,485.64
Century EngineeringOctober 29, 2025148038$2,625.22
Century EngineeringDecember 23, 2025149592$343.60

The two lighting lines total $47,229.26. The two Phase I inspection lines total $2,968.82. The vendor export’s last check date is July 8, 2026.

Timeline 16

Dates follow the cited records; document dates are labeled separately.

  1. August 9, 2022

    Council identifies an earlier appropriation for Habersham

    Council listed Habersham among the projects with earlier appropriations. Its adopted FY2023–27 capital plan identifies $581,588 in FY2023 grant funding for construction. That earlier plan establishes a funding history. The balance still available when Purchasing created the April 2026 order remains unverified.

  2. October 22, 2024

    Council names Boykin in the four-intersection plan

    During a right-of-way hearing, Council identified Jefferson Avenue at Boykin Lane among four intersections in the Habersham plan. The hearing concerned a landscape easement at 900 Bland Boulevard.

  3. March 21, 2025

    An $818 certificate-of-take entry matches the Council valuation

    Council valued 2,376 square feet of landscape easement at 900 Bland Boulevard at $818. A March 21 City register entry for the same amount names the address and identifies a certificate of take. The City is the listed payee. A separate January 23, 2026 entry pays $30,455 to the Villages of Kiln Creek Owners Association and identifies UPC 108723. Its description gives no purpose. Invoice 1936848 or the settlement instrument would establish what that later amount covered.

  4. May 9, 2025

    Boykin had already been crossed out of the first bid

    IFB 25-3991-6256 named three intersections. The two original Boykin sheets already carried the same red crosses and N.I.C. labels visible in the January 2026 rebid. All six PDF marks carry February 27, 2025 creation dates. The May publication establishes when bidders could see the exclusion. Identifying who authorized it and why requires the underlying design decision.

  5. May–December 2025

    Four vendor entries match two Engineering payment totals

    Virginia Electric and Power received $29,743.62 on May 21 and $17,485.64 on June 6 for streetlights, totaling $47,229.26. Century Engineering received $2,625.22 on October 29 and $343.60 on December 23 for inspection, totaling $2,968.82. Those totals match the two Engineering tracker rows. The vendor register ends July 8, 2026, before the July 20 start displayed for Allan Myers.

  6. June 26, 2025

    A separate agreement assigns the Boykin pedestrian refuge to Costco

    Article III makes Costco responsible for designing, building and initially paying for the off-site improvements. Exhibit A includes a raised pedestrian refuge on the north side of the Jefferson/Boykin intersection. The agreement documents responsibility for that crossing. It gives no reason for the City’s earlier bid exclusion.

  7. July 3, 2025

    Purchasing cancels the original solicitation

    The City said the first solicitation was canceled and its procurement records were sealed. It gave no reason in the notice. Both the May 2025 and January 2026 bid packages already omit Boykin from their advertised work.

  8. January 2026 rebid

    The bid drawings explain the fourth intersection

    The rebid names Jefferson at Brick Kiln Boulevard and Walmart Way, Jefferson at Habersham Drive, and Habersham at Chatham Drive. Attachment B also depicts Jefferson at Boykin Lane. The roadway and signal sheets for Boykin are crossed out in red and marked “N.I.C.” The tracker’s four-intersection description therefore includes a location omitted from the advertised work.

  9. January 29, 2026

    Purchasing corrects two bid quantities before closing

    Purchasing changed the scheduled hydrant and six-inch gate valve quantities from 30 each to one each before bidding closed. The evaluation tabulation confirms both firms priced one of each. Allan Myers bid $10,000 for the hydrant and $5,000 for the valve. Parkway Grading bid $11,770 and $3,115 respectively. Field measurements and vouchers would show the installed quantities and charges.

  10. April 20, 2026

    The City creates a $5,987,777 purchase order for Allan Myers

    Purchase order 20262818 identifies Allan Myers, requisition 2768 and UPC 108723. The creation date is 22 days before the May 12 vote on $4,768,520. The register shows a June 26 change date, $5,987,777 ordered, $0 liquidated and the full order balance. Council had documented earlier appropriations. The April 20 available balance and the date each accounting line was funded remain open.

  11. May 12, 2026

    Council agenda identifies two equal funding components

    The $4,768,520 item combines $2,384,260 in state revenue sharing with $2,384,260 in general obligation bond funding.

  12. May 12, 2026

    The local match draws on other capital project balances

    The packet ties the project to pedestrian refuge areas, an eight-foot sidewalk, lighting, signs/signals and drainage. Of the $2,384,260 local match, $1,387,396.29 came from the proposed reassignment of Tech Center Parkway Extension funds and $339,603.83 from Jefferson Avenue/Center Avenue; remaining balances made up the rest. The equal state match is separate.

  13. May 12, 2026

    Council approves the transfer; largest source already shows closeout

    Council's voting register records a 7–0 approval of the $4,768,520 item. The City tracker for the Tech Center Parkway Extension Phase II reports construction closeout in June 2023 and project closeout in July 2025, before the $1,387,396.29 transfer. That is about 58% of the local match. It is not proof of an unencumbered balance. The $339,603.83 Jefferson and Center row uses J2608, which the City tracker also uses for its signal installation and upgrade program. A ledger is needed to tell which subproject supplied that money.

  14. August 6, 2026 release

    The order splits equally between two funds

    Fund 4300 and Fund 4104 each account for $2,993,888.50 of the construction order. Each amount is $609,628.50 above its corresponding share of the May appropriation. The purchase order shows the later coding across nine lines. Reconciling the balance on the creation date requires the pre-vote ledger and the June order history.

  15. August 11, 2026

    The bid tabulation confirms both competing prices

    The official tabulation lists Allan Myers at $5,987,777 and Parkway Grading at $6,377,798.85, a difference of $390,021.85. Procurement identifies Allan Myers as selected. Its bid, the April purchase order and the Engineering tracker agree on the amount. Actual progress payments require separate records.

  16. October–November 2026 review

    Two inspection records differ by $2,000

    The April 21 Century Engineering order for Phase II inspection shows $380,386.82 and closed after a July 9 change. The tracker lists $382,386.82 under Kleinfelder. The City’s register directs users from Century’s citywide contract to Kleinfelder’s. An October 9 Kleinfelder order is for the exact earlier amount, $380,386.82. The November export omits project descriptions, so its connection to Habersham and the reason for the $2,000 difference remain open. No matching payment was verified.

Documents 23

Showing 1–23 of 23 reviewed records.

  • OtherSource link

    City Council: May 12, 2026 agenda

    Public body
    City of Newport News
    Department / subject
    Newport News City Council
    Document date
    May 12, 2026

    Publisher source used in the habersham intersections: funding, construction and pedestrian safety case. See the case timeline for the specific fact this source supports.

    Source notes

    Linked to the original publisher. Reviewed November 20, 2026; a tracker or agenda is not independent proof of payment, completion or adoption.

  • OtherSource link

    City project tracker: Habersham area improvements

    Public body
    City of Newport News
    Department / subject
    Newport News Engineering
    Document date
    Date not specified

    Publisher source used in the habersham intersections: funding, construction and pedestrian safety case. See the case timeline for the specific fact this source supports.

    Source notes

    Linked to the original publisher. Reviewed November 20, 2026; a tracker or agenda is not independent proof of payment, completion or adoption.

  • Contracts & purchasingSource link

    Habersham area improvements rebid 26-2768-6256

    Public body
    City of Newport News
    Department / subject
    Newport News Purchasing
    Document date
    January 5, 2026

    Habersham area improvements rebid 26-2768-6256. Overview, summary and bid timeline for UPC 108723.

    Source notes

    Newport News Purchasing. Overview, summary and bid timeline for UPC 108723.

  • Contracts & purchasingSource link

    Habersham rebid drawings and specifications

    Public body
    City of Newport News
    Department / subject
    Newport News Purchasing
    Document date
    Date not specified

    Habersham rebid drawings and specifications. Downloads, Attachment B. PDF page 37 is roadway sheet 8 and PDF page 46 is signal sheet 12(4). Both show Jefferson at Boykin. PDF page 47 is the Habersham and Chatham signal plan.

    Source notes

    Newport News Purchasing. Downloads, Attachment B. PDF page 37 is roadway sheet 8 and PDF page 46 is signal sheet 12(4). Both show Jefferson at Boykin. PDF page 47 is the Habersham and Chatham signal plan.

  • Contracts & purchasingArchived file

    Jefferson Avenue at Boykin Lane in the Habersham rebid drawings

    Public body
    City of Newport News
    Department / subject
    Newport News Purchasing
    Document date
    Date not specified

    Two original plan sheets from Attachment B to rebid 26-2768-6256. Page 1 is roadway sheet 8 (source PDF page 37). Page 2 is signal sheet 12(4) (source PDF page 46). Both show the red cross and N.I.C. notation in the posted drawings.

    Preview PDF
    Source notes & file details

    Two original plan sheets from Attachment B to rebid 26-2768-6256. Page 1 is roadway sheet 8 (source PDF page 37). Page 2 is signal sheet 12(4) (source PDF page 46). Both show the red cross and N.I.C. notation in the posted drawings.

    File: habersham-boykin-lane-rebid-plan-sheets.pdf

  • Meetings & decisionsSource link

    Council identifies Boykin in the Habersham plan and values the 900 Bland easement

    Public body
    City of Newport News
    Department / subject
    City Council
    Document date
    October 22, 2024

    Adopted minutes identify four intersections in the plan, describe the landscape easement at 900 Bland Boulevard and record the vote.

    Source notes

    Regular meeting, public hearings item E.7. The council narrative describes the easement as 2,376 square feet valued at $818.

  • Contracts & purchasingSource link

    Boykin roadway and signal sheets in the original Habersham bid

    Public body
    City of Newport News
    Department / subject
    Office of Purchasing
    Document date
    May 9, 2025

    The first bid package shows the roadway and signal sheets crossed out at Jefferson Avenue and Boykin Lane.

    Source notes

    Original department / subject label: Purchasing

    Original IFB 25-3991-6256, Attachment B, PDF pages 37 and 46 of 77. The road and signal sheets render identically to the corresponding rebid pages. The six red PDF annotations have February 27, 2025 creation timestamps. Full source file SHA-256 35a8d0a71480060016a8a609acc2c79af732b3ef163bf24630f5b90468e2842c.

  • Contracts & purchasingArchived file

    Costco’s responsibility for Boykin Lane and the EDA payment conditions

    Public body
    City of Newport News
    Department / subject
    Economic Development Authority
    Document date
    June 26, 2025

    Four pages from the signed EDA–Costco agreement identify the proposed development, assign the off-site work, define the payment conditions and list the Boykin crossing in Exhibit A.

    Why this record matters

    Four-page excerpt from the signed agreement, beginning with the definitions and ending with Exhibit A. Each page is reproduced from the City’s released PDF.

    Preview PDF
    Source notes & file details

    Unaltered page images from the publicly released participation agreement. Excerpt pages 1–4 reproduce physical PDF pages 2, 4, 5 and 15. The last page is Exhibit A, printed page 14. For the complete signed agreement open the June 26, 2025 file on the City release page.

    File: costco-boykin-offsite-agreement-excerpt.pdf

  • Budget & financePublic release index

    Habersham project entries in the City vendor payment register

    Public body
    City of Newport News
    Department / subject
    Finance / Office of Purchasing
    Document date
    July 16, 2026

    Invoice-net entries for streetlight relocation, engineering inspection, the 900 Bland certificate of take and the Kiln Creek owners association.

    Source notes

    Original department / subject label: Finance / Purchasing

    G017326-070826, 2024_-_2026_Vendor_Payments.xlsx, Vendor Payments tab. Excel rows 92038, 105526, 110570, 141785, 154832 and 160769, counting the header as row 1. Check dates in the released workbook run from January 2, 2024 through July 8, 2026. Totals use Invoice Net on the specified lines.

  • Contracts & purchasingSource link

    Purchasing cancels the first Habersham bid

    Public body
    City of Newport News
    Department / subject
    Office of Purchasing
    Document date
    July 3, 2025

    The notice cancels the solicitation and says the procurement records were sealed.

    Source notes

    Original department / subject label: Purchasing

    Official Notice 1, posted July 3, 2025 at 3:03 p.m. The notice gives no reason for cancellation.

  • Budget & financePublic release index

    City purchase orders for Habersham construction and Phase II inspection

    Public body
    City of Newport News
    Department / subject
    Finance / Office of Purchasing
    Document date
    August 6, 2026

    The Allan Myers order names UPC 108723 and itemizes nine account allocations. A separate Century Engineering order covers Phase II construction engineering and inspection.

    Source notes

    Original department / subject label: Finance / Purchasing

    G017871-080426, Purchase_Order_Inquiry_02.01.2026-08.06.2026.xlsx, MUNIS Purchase Order Inquiry. Excel rows 2384–2402 (PO 20262818) and 2444–2448 (PO 20262826), header counted as row 1. Header, item and accounting rows describe the same order. SHA-256 aa8b430263665bc1bf5aa99f7d52220c66e121faa0157a6c6def32d13573e4b0.

  • Meetings & decisionsSource link

    Council’s 2022 Habersham revenue-sharing funding discussion

    Public body
    City of Newport News
    Department / subject
    City Council
    Document date
    August 9, 2022

    Council’s August 2022 meeting record identifies earlier appropriations for UPC 108723 and describes the local bond match.

    Source notes

    PDF labeled Draft, item 5, printed pages 23–24. The discussion identifies Habersham by name and UPC and records the vote on the VDOT resolution. It does not give the unspent balance in 2026.

  • Budget & financePublic release index

    City contract register cross-reference for Century and Kleinfelder inspection services

    Public body
    City of Newport News
    Department / subject
    Finance / Office of Purchasing
    Document date
    October 21, 2026

    Century’s agreement directs users to another contract number, which the City lists under Kleinfelder. These are citywide contracts.

    Source notes

    Original department / subject label: Finance / Purchasing

    G019711-101626, City_of_Newport_News_Contracts.xlsx, MUNIS Contracts tab. Excel row 14240 identifies Century under 22-2648-04 and directs users to 22-2648-94. Row 14318 lists 22-2648-94 under Kleinfelder. These rows give no Habersham-specific task amendment or payment amount.

  • Contracts & purchasingArchived file

    Official bid tabulation for the Habersham rebid

    Public body
    City of Newport News
    Department / subject
    Finance / Office of Purchasing
    Document date
    August 11, 2026

    Eight-page City evaluation with the Allan Myers and Parkway Grading prices for all 94 bid items in the Habersham rebid.

    Why this record matters

    Complete original bid tabulation. See page 1 for the competing totals and page 7 for the corrected line-item quantities.

    Preview PDF
    Source notes & file details

    Original department / subject label: Finance / Purchasing

    G018004-081126, 26-2768-6256__Bid_tabulation.pdf. Original PDF. Pages 1 and 8 list overall totals. Page 7 lists one fire hydrant and one six-inch gate valve for each bidder. The City identified Allan Myers as selected on the procurement results page.

    File: habersham-official-rebid-tabulation.pdf

  • Contracts & purchasingPublic release index

    October 9 Kleinfelder order in the City purchasing register

    Public body
    City of Newport News
    Department / subject
    Finance / Office of Purchasing
    Document date
    November 5, 2026

    The November City release lists an October 9 purchase order under Kleinfelder for $380,386.82. Its eight-column export does not identify the project.

    Source notes

    Original department / subject label: Finance / Purchasing

    G019974-110226, FOIA_PO_S_7.26_TO_11.26.xlsx, PURCHASE_ORDER_INQUIRY, Excel row 1503. PO 20271601, status printed, ordered amount and balance each $380,386.82. Project, contract and scope fields are absent from the export. Source workbook SHA-256 82f7f0df9c2ded880cf3967d8bd5f1e38e888dae9a75c2bea5dabfde973c53c8.

  • Budget & financeSource link

    Adopted FY 2023 - FY 2027 CIP

    Public body
    City of Newport News
    Department / subject
    Budget and Evaluation
    Document date
    Date not specified

    Capital improvements planning document published by the City of Newport News.

    Source notes

    Original department / subject label: Budget & Evaluation

    City of Newport News Document Center: Budget & Evaluation / Capital Improvements Plan. Document ID 31754. City listing: last uploaded Jul 23, 2024; size 5339 KB. Checked October 1, 2026. Upload date is not the document issue date. The source link opens the City’s maintained copy.

News story 0

No news story is currently linked to this case.

Open questions 6

  • Funding on the day of the construction order

    The April 20 pre-encumbrance ledger for J3050, budget entries before and after the May 12 vote, and the June 26 purchase-order change history.

    Likely custodian: Newport News Engineering; Finance

    The purchase order identifies the amount, dates and account coding. The ledger would establish available authority when the City created the order.

    Submit this record
  • Final construction scope

    Approved design revision or scope-allocation memorandum explaining the original Boykin strikeout, any signed Allan Myers change order restoring work there, and the separate Costco as-built plan and City/VDOT acceptance.

    Likely custodian: Newport News Engineering; VDOT

    The first bid establishes the exclusion by May 2025. The Costco agreement identifies a separate delivery obligation. The actual sign-offs would settle who built and accepted each item.

    Submit this record
  • Reconcile the transfers with closeout and subproject accounts

    Posted transfer journal, encumbrance release and local balance at Tech Center closeout; ledger crosswalk for Jefferson and Center account J2608.

    Likely custodian: City Budget; Engineering

    Project closeout narrows the timing of the largest transfer but does not establish free cash or resolve the separate signals account.

    Submit this record
  • Measure the safety result

    Intersection-specific baseline, completion date and comparable crash, crossing and pedestrian-count data after opening

    Likely custodian: City Engineering; Virginia Department of Transportation

    Test exposure and safety at the actual crossing, not just citywide trends.

    Submit this record
  • Reconcile the two Phase II inspection amounts

    The detailed October 9 order 20271601 and requisition, July 9 closeout for Century PO 20262826, the project task order under Kleinfelder agreement 22-2648-94, any amendments, and payment vouchers.

    Likely custodian: Newport News Purchasing, Engineering and Finance

    Determine whether the $2,000 reflects changed scope, a replacement order or a tracker entry, then match any expense to an approved voucher.

    Submit this record
  • Payment and any later Boykin change

    Allan Myers pay applications, certified vouchers and executed scope changes keyed to PO 20262818 and UPC 108723 after July 8, 2026.

    Likely custodian: Newport News Engineering and Finance

    The July vendor register predates the tracker start date. The purchase-order balance and tracker display cover different questions.