SCC explanation of large-load customer protections and Rider T1 reforms
Official explanation of separate large-load rates, contract and minimum-payment safeguards, and the framework for assigning direct-connect transmission costs.
- Public body
- Virginia state agencies
- Document date
- September 3, 2026
- Record type
- Source link
Record details
Document details
- Department / subject
- Virginia State Corporation Commission
- Public body
- Virginia state agencies
Source notes
Source-only SCC webpage. Selected data-center and Rider T1 sections checked October 30. Some provisions begin January 1, 2027; the supplemental direct-connect proceeding remains distinct from an implemented final policy. No complete later-order review is claimed.