Denbigh and I-64: two phases, construction funding and access

Overview

VDOT estimates $281.5 million across both phases. For Phase 2, the regional commission reported $4.45 million spent through August 24, 2026, all on preliminary engineering. The construction funding amendment remains open.

Background & source notes

Distinguish the Phase 1 design-build contract from total interchange costs, and follow access around Richneck Road. A public VDOT Facebook construction announcement pointed to this project.

Source notes and limitations

All spending figures cited here concern Phase 2 and have specific reporting cutoffs. Construction funding and local access changes require separate records.

Case details

Page options

Where things stand

Updated

From the reviewed timeline

Phase 2 remains in design on VDOT’s project page

November 20, 2026

VDOT lists anticipated award and construction start in mid-2030 and completion in mid-2034. Phase 1 materials describe the planned Richneck connection closure.

View timeline entry and sources

Open question

Phase 2 funding

Signed HRTAC–VDOT construction funding amendment for UPC 123656 and the first regional obligations report that lists construction.

View all 3 open questions

Money Trail

No itemized funding entries are published for this case.

Evidence

Timeline 6

Dates follow the cited records; document dates are labeled separately.

  1. April 2026

    Regional financing and highway access are separate decisions

    The regional Finance Committee packet lists $26,643,026 for Phase 2. The Commonwealth Transportation Board materials separately address changes to limited-access boundaries. Neither document replaces the $161,420,044 Phase 2 construction funding amendment identified in the financial plan.

  2. April 30, 2026

    VDOT sets a two-phase baseline

    The plan estimates $281,483,171 across both phases. The $58,335,882 Phase 1 design-build contract is a subset. The plan says a $161,420,044 Phase 2 construction funding amendment is needed before award.

  3. May 2026 regional program

    The schedule and obligation table tell different parts of the story

    For Phase 2, UPC 123656, the regional program estimates $161,420,044 for construction and forecasts physical construction from April 2030 to August 2034. The same entry's scheduled-obligations table lists only engineering and right of way, not construction. The date forecast and estimated construction amount are not evidence that the regional construction amendment was executed.

  4. August 24, 2026

    All reported Phase 2 spending was for preliminary engineering

    The regional commission reported $4,451,929 spent on preliminary engineering through August 24, up $921,813 from March 25. Both statements recorded zero expenditures for right of way and construction. The August statement still carried $161,420,044 as the construction budget.

  5. September 30, 2026

    Year-end report confirms the regional allocation

    The commission reported a cumulative $26,643,026 in Hampton Roads Transportation Fund allocations for Phase 2 through June 30. The construction budget appears separately in the project report. The year-end allocation table does not record the execution of a construction funding amendment.

  6. November 20, 2026

    Phase 2 remains in design on VDOT’s project page

    VDOT lists anticipated award and construction start in mid-2030 and completion in mid-2034. Phase 1 materials describe the planned Richneck connection closure.

Documents 9

Showing 1–9 of 9 reviewed records.

  • OtherSource link

    VDOT: I-64 at Denbigh financial plan

    Public body
    Virginia state agencies
    Department / subject
    Virginia Department of Transportation
    Document date
    April 30, 2026

    Publisher source used in the denbigh and i-64: two phases, construction funding and access case. See the case timeline for the specific fact this source supports.

    Source notes

    Linked to the original publisher. Reviewed November 20, 2026; a tracker or agenda is not independent proof of payment, completion or adoption.

  • OtherSource link

    VDOT: I-64 at Denbigh Phase 1

    Public body
    Virginia state agencies
    Department / subject
    Virginia Department of Transportation
    Document date
    Date not specified

    Publisher source used in the denbigh and i-64: two phases, construction funding and access case. See the case timeline for the specific fact this source supports.

    Source notes

    Linked to the original publisher. Reviewed November 20, 2026; a tracker or agenda is not independent proof of payment, completion or adoption.

  • OtherSource link

    VDOT: I-64 at Denbigh Phase 2

    Public body
    Virginia state agencies
    Department / subject
    Virginia Department of Transportation
    Document date
    Date not specified

    Publisher source used in the denbigh and i-64: two phases, construction funding and access case. See the case timeline for the specific fact this source supports.

    Source notes

    Linked to the original publisher. Reviewed November 20, 2026; a tracker or agenda is not independent proof of payment, completion or adoption.

  • OtherSource link

    HRTAC Finance Committee: Denbigh Phase 2 project amount

    Public body
    Virginia state agencies
    Department / subject
    Hampton Roads Transportation Accountability Commission
    Document date
    April 16, 2026

    Finance agenda lists Phase 2 separately; an agenda amount is not construction authorization.

    Source notes

    Original publisher. Finance agenda lists Phase 2 separately; an agenda amount is not construction authorization.

  • OtherSource link

    HRTPO: FY 2027–2030 transportation program, Denbigh Phase 2

    Public body
    Virginia state agencies
    Department / subject
    Hampton Roads Transportation Planning Organization
    Document date
    Date not specified

    Shows the phase construction estimate and schedule but lists no construction row in the scheduled-obligations table for this UPC.

    Source notes

    Original publisher. Shows the phase construction estimate and schedule but lists no construction row in the scheduled-obligations table for this UPC.

  • Budget & financeSource link

    HRTAC September 2026 Commission packet and project expenditures

    Public body
    Virginia state agencies
    Department / subject
    Hampton Roads Transportation Accountability Commission
    Document date
    September 17, 2026

    HRTAC September 2026 Commission packet and project expenditures. PDF page 110, September executive report page 17, UPC 123656 financial summary as of August 24.

    Source notes

    Hampton Roads Transportation Accountability Commission. PDF page 110, September executive report page 17, UPC 123656 financial summary as of August 24.

  • Budget & financeSource link

    HRTAC April 2026 Commission packet and project expenditures

    Public body
    Virginia state agencies
    Department / subject
    Hampton Roads Transportation Accountability Commission
    Document date
    April 16, 2026

    HRTAC April 2026 Commission packet and project expenditures. PDF page 167, April executive report page 18, UPC 123656 financial summary as of March 25.

    Source notes

    Hampton Roads Transportation Accountability Commission. PDF page 167, April executive report page 18, UPC 123656 financial summary as of March 25.

  • Budget & financeSource link

    HRTAC FY 2026 report to the Joint Commission on Transportation Accountability

    Public body
    Virginia state agencies
    Department / subject
    Hampton Roads Transportation Accountability Commission
    Document date
    September 30, 2026

    HRTAC FY 2026 report to the Joint Commission on Transportation Accountability. Printed page 9 (PDF page 10), HRTF allocations through June 30, row for UPC 123656.

    Source notes

    Hampton Roads Transportation Accountability Commission. Printed page 9 (PDF page 10), HRTF allocations through June 30, row for UPC 123656.

News story 0

No news story is currently linked to this case.

Open questions 3

  • Phase 2 funding

    Signed HRTAC–VDOT construction funding amendment for UPC 123656 and the first regional obligations report that lists construction.

    Likely custodian: VDOT; Hampton Roads Transportation Accountability Commission

    The regional program lists construction timing and costs but lacks a construction obligation line for Phase 2.

    Submit this record
  • Local access

    Detour plan, traffic counts and crash reporting after changes

    Likely custodian: VDOT; Newport News Engineering

    Test the effect on nearby streets instead of relying on projected benefits.

    Submit this record
  • Funding after the reported cutoffs

    Phase 2 project agreements, subsequent allocation changes and later expense statements by phase for UPC 123656.

    Likely custodian: HRTAC; VDOT

    The June allocation and August expense statement establish a baseline for tracing later commitments, payments and progress.