Denbigh Fishing Pier Replacement — City project tracker 1202
The City lists a $406,677 construction contract and $394,140 paid to date, plus $102,175 in professional-services contract value and $95,903.36 paid to date.
Why this record matters
The tracker reconciles $490,043.36 paid across two pier contracts: The two listed contracts total $508,852. The tracker shows $490,043.36 paid, a difference of $18,808.64. The construction difference is $12,537 and the design difference is $6,271.64. The project description excludes the timber walkway. The final ledger and pay applications would establish the whole-project cost and explain the two differences.
Source notes
Official project tracker reviewed November 14, 2026. The table reports contract and paid-to-date amounts. Closeout is marked complete in the schedule. Final ledger and acceptance records remain needed.