Denbigh Fishing Pier: reopening, delivery and contract closeout

Overview

Council approved a parks funding package that included $500,000 for Denbigh pier construction. Parks announced that the reconstructed pier had reopened. The City tracker shows $490,043.36 paid across construction and design contracts. Final acceptance and project accounting remain open.

Background & source notes

Follow the replacement of the timber pier at Denbigh Park from the professional-services contract through construction, reopening and closeout. Compare the facility that reopened with the contract scope and the City’s underlying payment records.

Source notes and limitations

The Parks announcement establishes public reopening. The tracker supplies reported schedule and payment fields. Final costs and public access outcomes depend on acceptance, ledger and operating records.

Case details

Page options

Where things stand

Updated

Reviewed finding

The tracker reconciles $490,043.36 paid across two pier contracts

November 14, 2026

The two listed contracts total $508,852. The tracker shows $490,043.36 paid, a difference of $18,808.64. The construction difference is $12,537 and the design difference is $6,271.64. The project description excludes the timber walkway. The final ledger and pay applications would establish the whole-project cost and explain the two differences.

Open question

What was the final cost of the pier replacement?

Project 1202 appropriation and program ledger, funding codes for both contracts, approved change orders, final pay applications, retainage and any unspent amount returned to the parks bond account.

View all 3 open questions

Money Trail

Compare the City tracker’s two cumulative paid-to-date amounts with the listed contract values. The displayed date is the date of review.

Denbigh pier construction and professional services

Reported entryAmountCity project record
Construction paid to dateCity of Newport News → Crofton Construction Services$394,140

The City tracker lists a $406,677 construction contract. The final invoice and ledger would explain any adjusted balance.

City tracker construction contract row Record details

Professional services paid to dateCity of Newport News → Moffatt and Nichol$95,903.36

The City tracker lists a $102,175 professional-services contract. Reconcile the paid-to-date figure to the final project ledger.

City tracker professional-services contract row Record details

Evidence

Timeline 6

Dates follow the cited records; document dates are labeled separately.

  1. August 28, 2023

    City tracker lists the start of professional services

    The tracker identifies Moffatt and Nichol’s professional-services contract at $102,175. The stated construction scope covers demolition and replacement of the timber pier, substructure and T section, with new adjacent piles and no-wake signage. The timber walkway is excluded in the scope description.

  2. January 9, 2024

    Council approves a parks package with $500,000 for pier construction

    The adopted minutes show seven ayes for a $1.87 million parks appropriation from the FY2024 bond authorization. The package included $500,000 for the pier’s replacement construction. The same record says the pier had been taken out of service in late 2022 because of safety concerns. The project ledger would show how the allocation was charged and whether professional services used the same funding.

  3. January 30, 2025

    City tracker lists Crofton’s construction contract

    The construction contract starts January 30 in the tracker and is listed at $406,677. The detailed schedule marks construction through May 19 and subsequent construction closeout through June 10. The contract row shows a different finish field, June 28.

  4. May 23, 2025

    Parks announces the reconstructed fishing pier is open

    The Parks Division announcement identifies the reconstructed pier and boat ramp as open for daily public use. The recreation guide lists Denbigh among its free saltwater fishing piers. The acceptance inspection and accessibility scope remain records to compare with public reopening.

  5. May 19, 2025 to August 9, 2025

    The tracker lists three distinct completion milestones

    The City tracker lists May 19 for the end of the construction phase, June 10 for the construction closeout phase and August 9 for project closeout. Parks announced public reopening on May 23. The construction contract line lists a June 28 finish. Final inspection and acceptance records would establish which milestone controlled warranty and final payment.

  6. November 14, 2026

    City tracker shows completion and $490,043.36 paid across two contracts

    The tracker marks project closeout 100% complete. It lists $394,140 paid against $406,677 for construction and $95,903.36 against $102,175 for professional services. These two rows sum to $508,852 in contract amounts and $490,043.36 in paid-to-date entries. Their $18,808.64 difference is a reconciliation point for final invoices and adjustments.

Documents 4

Showing 1–4 of 4 reviewed records.

  • Contracts & purchasingSource link

    Denbigh Fishing Pier Replacement — City project tracker 1202

    Public body
    City of Newport News
    Department / subject
    Engineering / Construction and Bridge
    Document date
    Date not specified

    The City lists a $406,677 construction contract and $394,140 paid to date, plus $102,175 in professional-services contract value and $95,903.36 paid to date.

    Why this record matters

    The tracker reconciles $490,043.36 paid across two pier contracts: The two listed contracts total $508,852. The tracker shows $490,043.36 paid, a difference of $18,808.64. The construction difference is $12,537 and the design difference is $6,271.64. The project description excludes the timber walkway. The final ledger and pay applications would establish the whole-project cost and explain the two differences.

    Source notes

    Official project tracker reviewed November 14, 2026. The table reports contract and paid-to-date amounts. Closeout is marked complete in the schedule. Final ledger and acceptance records remain needed.

  • OtherSource link

    Newport News Parks announces the reconstructed Denbigh pier is open

    Public body
    City of Newport News
    Department / subject
    Newport News Parks Division
    Document date
    May 23, 2025

    The public Parks Division post announces the restored fishing pier and confirms daily access hours for the pier and boat ramp.

    Why this record matters

    Reopening is documented and two reported payments can be reconciled: Parks announced reopening on May 23, 2025. The City tracker shows $394,140 paid for construction and $95,903.36 for professional services. Final pay applications and the project ledger would resolve the balance shown against both contract amounts.

    Source notes

    Official public Facebook reopening announcement dated May 23, 2025. Final contract acceptance and public opening are distinct milestones.

  • OtherSource link

    Newport News Parks lists public fishing pier access

    Public body
    City of Newport News
    Department / subject
    Parks, Recreation and Tourism
    Document date
    Date not specified

    The City’s recreation guide lists Denbigh Park among its free saltwater fishing piers and provides public operating hours.

    Source notes

    Original department / subject label: Parks and Recreation

    Consult the public Parks page for site access. The Denbigh opening notice supplies the date of the public reopening.

  • Meetings & decisionsSource link

    January 9, 2024 adopted Council minutes: school and parks appropriations

    Public body
    City of Newport News
    Department / subject
    City Council
    Document date
    January 9, 2024

    Appropriations items 2 and 3 record the FY2024 bond-funded parks package, including $500,000 for Denbigh pier replacement construction, and the school funding vote.

    Why this record matters

    $500,000 in construction funding and three closeout milestones are documented: The January 2024 minutes identify the construction allocation and confirm the old pier’s safety closure. The City tracker distinguishes the May 19 end of construction from June 10 construction closeout and August 9 project closeout. Those records provide a timeline to check against the May 23 reopening and the final acceptance and payment files.

    Source notes

    Official adopted minutes. See appropriations item 2 for the Denbigh pier allocation and seven ayes and item 3 for the school allocation.

News story 0

No news story is currently linked to this case.

Open questions 3

  • What was the final cost of the pier replacement?

    Project 1202 appropriation and program ledger, funding codes for both contracts, approved change orders, final pay applications, retainage and any unspent amount returned to the parks bond account.

    Likely custodian: Engineering, Purchasing and City Finance

    The $500,000 construction allocation, contract values and paid-to-date amounts describe separate stages. The ledger would show final spending from each funding source.

    Submit this record
  • When and how did the City accept the work?

    May 2025 substantial completion and public reopening approval, final structural and accessibility inspection, punch-list clearance, acceptance notice and warranty start, with any items completed during the later June and August closeout periods.

    Likely custodian: Engineering and Parks and Recreation

    The tracker provides project and contract milestone dates. The signed acceptance records would identify what the City accepted and when.

    Submit this record
  • What changed for residents using the pier?

    Available usage counts, accessibility and maintenance requests, operations and maintenance schedule and any post-opening temporary closures.

    Likely custodian: Parks and Recreation

    Check whether the replacement restored reliable public fishing access and whether follow-up work has been needed.