Copeland Park pump station: construction pricing and water continuity

Overview

Newport News prequalified five firms for the Copeland Park pump station project. The capital plan schedules $15 million for construction across five years. The final construction manager and guaranteed price remain unverified.

Background & source notes

Track drinking-water pumping improvements at Copeland Park, the selection and final price, and measures to protect service during construction.

Source notes and limitations

The 2025 replacement-pump solicitation, the five-firm shortlist and the capital plan each concern a different decision. A final construction award, guaranteed price, payments and acceptance remain unverified.

Case details

Page options

Where things stand

Updated

From the reviewed timeline

Council authorizes construction manager at risk

March 10, 2026

The resolution authorizes the approach for the aging installation and supply continuity constraints. It does not identify a winning contractor or set a guaranteed maximum price.

View timeline entry and sources

Open question

Identify the contractor and negotiated price

Second-stage request for proposals, selection notice, signed agreement and subsequent guaranteed maximum price.

View all 4 open questions

Money Trail

No itemized funding entries are published for this case.

Evidence

Timeline 6

Dates follow the cited records; document dates are labeled separately.

  1. February 7, 2025

    The City separately sought replacement pumps for the existing station

    The City solicited three replacement pumps for Copeland Park. Purchasing said the existing equipment was about 40 years old and expected replacements to restore capacity and redundancy. The solicitation documents an earlier equipment purchase process. Delivery, installation and any credit toward the later station project remain unverified.

  2. 2025

    Council funds preliminary engineering

    Resolution 13885-25 appropriates $1 million for engineering; it is not a construction budget.

  3. March 10, 2026

    Council authorizes construction manager at risk

    The resolution authorizes the approach for the aging installation and supply continuity constraints. It does not identify a winning contractor or set a guaranteed maximum price.

  4. Spring 2026

    Procurement moves from method approval to qualifications

    The purchasing portal identifies an RFQ for a construction manager at risk. It is a qualifications step, not a signed construction deal. The preceding $1 million appropriation packet breaks the engineering work into $364,344 for investigation and $635,656 for design and coordination; it anticipates separate future appropriations.

  5. FY 2027–31 capital plan

    The City shifts planned construction spending into later years

    The FY26–30 plan put $1 million in FY26 design and $5 million each in FY27, FY28 and FY29 construction. The FY27–31 plan still budgets $15 million for construction, now $2 million in FY27, $4 million a year from FY28 through FY30 and $1 million in FY31. The difference between $16 million and $15 million includes FY26 design leaving the five-year window; it does not show project savings or a contractor price.

  6. November 20, 2026 procurement review

    The City identifies five firms that qualified for the next stage

    The City’s results name Alberici Constructors, Inc., Clark Water, LLC, Crowder Construction Company, MEB General Contractors, Inc. and Ulliman Schutte Construction, LLC. Its award note says the firms were prequalified. The solicitation says shortlisted firms would receive a request for proposals. The public results identify the five candidates but do not name a final construction manager or give a construction price.

Documents 8

Showing 1–8 of 8 reviewed records.

  • OtherSource link

    City of Newport News: 2025 adopted resolutions

    Public body
    City of Newport News
    Department / subject
    Newport News City Council
    Document date
    Date not specified

    Publisher source used in the copeland park pump station: construction pricing and water continuity case. See the case timeline for the specific fact this source supports.

    Source notes

    Linked to the original publisher. Reviewed November 20, 2026; a tracker or agenda is not independent proof of payment, completion or adoption.

  • OtherSource link

    City Council: Copeland Park appropriation item

    Public body
    City of Newport News
    Department / subject
    Newport News City Council
    Document date
    Date not specified

    Publisher source used in the copeland park pump station: construction pricing and water continuity case. See the case timeline for the specific fact this source supports.

    Source notes

    Linked to the original publisher. Reviewed November 20, 2026; a tracker or agenda is not independent proof of payment, completion or adoption.

  • OtherSource link

    City Resolution 13954-26: procurement method

    Public body
    City of Newport News
    Department / subject
    Newport News City Council
    Document date
    March 10, 2026

    Publisher source used in the copeland park pump station: construction pricing and water continuity case. See the case timeline for the specific fact this source supports.

    Source notes

    Linked to the original publisher. Reviewed November 20, 2026; a tracker or agenda is not independent proof of payment, completion or adoption.

  • Budget & financeSource link

    Adopted FY 2026 - FY 2030 CIP

    Public body
    City of Newport News
    Department / subject
    Budget and Evaluation
    Document date
    Date not specified

    Capital improvements planning document published by the City of Newport News.

    Source notes

    Original department / subject label: Budget & Evaluation

    City of Newport News Document Center: Budget & Evaluation / Capital Improvements Plan. Document ID 41147. City listing: last uploaded Jun 11, 2026; size 5818 KB. Checked October 1, 2026. Upload date is not the document issue date. The source link opens the City’s maintained copy.

  • Budget & financeSource link

    FY 2027 - FY 2031 Adopted CIP - Final

    Public body
    City of Newport News
    Department / subject
    Budget and Evaluation
    Document date
    Date not specified

    Capital improvements planning document published by the City of Newport News.

    Source notes

    Original department / subject label: Budget & Evaluation

    City of Newport News Document Center: Budget & Evaluation / Capital Improvements Plan. Document ID 44461. City listing: last uploaded Apr 17, 2026; size 2935 KB. Checked October 1, 2026. Upload date is not the document issue date. The source link opens the City’s maintained copy.

News story 0

No news story is currently linked to this case.

Open questions 4

  • Identify the contractor and negotiated price

    Second-stage request for proposals, selection notice, signed agreement and subsequent guaranteed maximum price.

    Likely custodian: Newport News Procurement; Waterworks

    The published qualifications results identify five eligible firms. A selection notice or contract would identify the firm chosen for the work.

    Submit this record
  • Continuity of water service

    Temporary pumping plan, commissioning criteria, aggregate outage or disruption logs, and final commissioning and acceptance records.

    Likely custodian: Newport News Waterworks

    Check how water service will be maintained without seeking sensitive operational details.

    Submit this record
  • Trace preconstruction fees and the final price

    Executed preconstruction contract, fee schedule, subsequent guaranteed maximum price and amendments.

    Likely custodian: Purchasing; Waterworks

    Determine which services each agreement covers and how the negotiated construction price compares with the capital plan.

    Submit this record
  • Reconcile the revised spending schedule with procurement

    Current scope baseline, schedule and cost estimate used for the negotiated preconstruction agreement and any guaranteed maximum price.

    Likely custodian: Waterworks; City Purchasing

    Show whether the new fiscal schedule reflects sequencing or a change in what the City plans to build.