Citywide traffic signal retiming: grant funding and travel delays

Overview

Newport News approved $1.35 million in federal and state funds to retime traffic signals. City Engineering reports a $1,121,046 purchase order. The public records reviewed so far leave actual payments, the final intersection list and changes in travel delays open.

Background & source notes

This case follows the City’s work to improve traffic flow by changing signal timing, coordination and phasing under VDOT project UPC 115519. The grant agreement form identifies Route 17 and Mercury Boulevard as an initial area of work and allows locations to change based on need and analysis. Engineering says it will select intersections based on funding, changing traffic and resident requests.

A November 2026 funding request for intelligent transportation systems includes signal equipment and some timing work under UPC 111081. Its separate identifier and local-matching requirements are relevant when checking expense and delivery records for retiming.

Source notes and limitations

The Council resolution establishes funding authority. The project tracker gives a staff-reported order amount and a contract row requiring reconciliation. The reviewed sources lack invoice, reimbursement and acceptance records. The initial geography may change, and measured results require actual activation dates and comparable before-and-after data. The November 10 funding item for UPC 111081 was reviewed as a staff proposal.

Case details

Page options

Where things stand

Updated

Reviewed finding

The City authorized $1.35 million for retiming

November 13, 2026

On October 28, 2025, Council separately authorized a VDOT agreement and appropriated $1.35 million for UPC 115519. The signed funding resolution assigns $1.08 million in federal revenue and $270,000 in state revenue to retiming. City staff describe reimbursement of eligible expenses and zero local match on this grant.

Open question

Which intersections received new timing plans?

Signed VDOT agreement and amendments, purchase order 20270936 and scope, prioritized intersection list, implementation dates and City acceptance of final timing plans.

View all 3 open questions

Retiming funds and procurement 3

The state and federal appropriations, the reported purchase order and the newer equipment upgrade each refer to a different accounting record.

Go to the data tables

The City authorized $1.35 million for retiming

On October 28, 2025, Council separately authorized a VDOT agreement and appropriated $1.35 million for UPC 115519. The signed funding resolution assigns $1.08 million in federal revenue and $270,000 in state revenue to retiming. City staff describe reimbursement of eligible expenses and zero local match on this grant.

The project tracker gives two different views of the contract

Engineering’s July 29 comment reports that purchase order 20270936 was issued to Kimley-Horn for $1,121,046. The same page shows $0.00 under both Contract Amount and Paid To Date for the named consultant. The signed order, accounts-payable ledger and VDOT reimbursement records would reconcile those fields.

The November intelligent transportation systems request uses a different project number

The November 10, 2026 staff packet identifies UPC 111081 and a proposed $1.25 million appropriation, including $250,000 from the local grant match. Its scope also mentions timing optimization, but the sources identify it separately from retiming under UPC 115519. Council passage of the November request is unverified.

Retiming appropriation and purchase order, UPC 115519
RecordAmountWhat the record establishes
Federal revenue$1,080,000Part of the Council appropriation
State revenue$270,000Part of the Council appropriation
Total retiming appropriation$1,350,000Spending authority for UPC 115519
Kimley-Horn purchase order 20270936$1,121,046Order amount reported in Engineering’s July 29 comment

The purchase order is shown against the funding for comparison. Actual spending and reimbursement require vouchers and payment records.

Timeline 4

Dates follow the cited records; document dates are labeled separately.

  1. October 28, 2025

    Council authorizes the retiming agreement

    The minutes record a 7–0 vote on Resolution 13920-25. The attached VDOT form identifies preliminary engineering, a proposed area near Route 17 and Mercury Boulevard, and no construction expense for this project.

  2. October 28, 2025

    Council appropriates $1.35 million for retiming

    Council passed Resolution 13921-25 by a 7–0 vote. The $2.625 million resolution covered three projects. Retiming’s share comprised $1.08 million in federal revenue and $270,000 in state revenue.

  3. July 29, 2026

    Engineering reports the Kimley-Horn purchase order

    The project tracker’s July 29 comment identifies order 20270936 for $1,121,046 and describes roughly two years of study and implementation with no construction. Its contract row shows $0.00 in both amount fields as reviewed November 13. The order and payment ledger would establish the amounts committed and paid.

  4. November 10, 2026

    Council agenda lists funding for a separate equipment and timing project

    Item 26-178 proposes appropriating $1 million in federal earmark money and $250,000 in local funds for UPC 111081. The staff packet ties the request to signal equipment, coordination and timing analysis. The Council vote remains to be verified.

Documents 7

7 of 7 reviewed records. Source links, source collections and release indexes are identified separately from archived copies.

  • Budget & financeSource link

    Adopted Resolution 13921-25: $1.35 million for signal retiming

    City of Newport News · City Council / EngineeringDocument date: October 28, 2025

    Two-page signed resolution appropriating $2,625,000 for three projects, with $1,350,000 assigned to the signal retiming project, UPC 115519.

    Why this record matters

    The City authorized $1.35 million for retiming: On October 28, 2025, Council separately authorized a VDOT agreement and appropriated $1.35 million for UPC 115519. The signed funding resolution assigns $1.08 million in federal revenue and $270,000 in state revenue to retiming. City staff describe reimbursement of eligible expenses and zero local match on this grant.

    Source notes

    Physical PDF page 1 lists $1,080,000 in federal revenue for retiming. Page 2 lists $270,000 in state revenue, the $1,350,000 project allocation and the date of passage.

  • Meetings & decisionsSource link

    Adopted Resolution 13920-25: VDOT agreements for signal retiming and two related projects

    City of Newport News · City Council / EngineeringDocument date: October 28, 2025

    Council authorizes three project administration agreements. The retiming agreement exhibit identifies UPC 115519, Route 17 and Mercury Boulevard, and the project funding estimate.

    Why this record matters

    Physical PDF pages 1–2 and 30. The attached agreement form gives the starting geography, preliminary engineering and VDOT oversight estimates.

    Source notes

    Physical PDF pages 1–2 show the resolution and passage. Appendix A on physical PDF page 30 gives the initial location and cost estimates. Council authorization and the attached form are evidence of authority to execute the VDOT agreement.

  • Meetings & decisionsSource link

    Council October 28, 2025 minutes: Dominion easement at Rock Landing Drive

    City of Newport News · City Council / City Clerk's OfficeDocument date: October 28, 2025

    Public-hearing item E.1 records adoption of the 11780 Rock Landing Drive easement for traffic-signal power. Jones, Bethany and Eley are among seven affirmative votes.

    Why this record matters

    Items G.8 and G.9 record the separate agreement and appropriation votes for three congestion and air-quality projects, including UPC 115519.

    Source notes

    Individual adopted minutes reviewed in the publisher’s HTML rendering. Bethany moved adoption and Long seconded. Source-only; the DOCX-shaped URL is not described as a downloaded PDF. The $1 bid concerns a utility easement supporting a City traffic project, not sale of the property.

  • Contracts & purchasingSource link

    City Engineering tracker for traffic signal retiming, UPC 115519

    City of Newport News · EngineeringDocument date: Date not specified

    Engineering’s July 29 comment reports a $1,121,046 Kimley-Horn purchase order for the retiming study and implementation. The separate contract row displays $0.00 in both amount fields.

    Why this record matters

    The project tracker gives two different views of the contract: Engineering’s July 29 comment reports that purchase order 20270936 was issued to Kimley-Horn for $1,121,046. The same page shows $0.00 under both Contract Amount and Paid To Date for the named consultant. The signed order, accounts-payable ledger and VDOT reimbursement records would reconcile those fields.

    Source notes

    Project description, July 29, 2026 comment and Contracts table reviewed November 13, 2026. The purchase-order figure is a commitment reported by staff. The contract row does not resolve the amount paid.

  • Budget & financeSource link

    Citywide ITS Upgrade funding request, November 10 Council item 26-178

    City of Newport News · EngineeringDocument date: November 10, 2026

    Engineering’s separate UPC 111081 funding item identifies a $1 million federal earmark award and a proposed $250,000 FY2027 local match, with data analysis, traffic-signal timing and equipment in scope.

    Why this record matters

    Separate UPC 111081. Pages 1–2 identify grant and local match. Page 4 contains the proposed resolution.

    Source notes

    Physical PDF pages 1–2 identify UPC 111081 and the proposed appropriation. Page 4 is the draft resolution. The project’s funding and execution records are separate from UPC 115519.

  • Meetings & decisionsSource collection

    City Council actions and resolutions — official collection index

    City of Newport News · City CouncilDocument date: Date not specified

    Council ordinances and resolutions grouped by meeting date.

    Why this record matters

    The City’s actions list was posted through October 27 when checked November 13, 2026. The November 10 packet is an agenda source.

    Source notes

    Official collection or access guide, not an individual archived document. Individual linked records have separate entries where reviewed. Collection contents can change, and this catalog does not mirror every attachment. Verified against the official publisher October 8, 2026.

Open questions 3

  • Which intersections received new timing plans?

    Signed VDOT agreement and amendments, purchase order 20270936 and scope, prioritized intersection list, implementation dates and City acceptance of final timing plans.

    Likely custodian: Newport News Engineering and VDOT

    Distinguish proposed locations from intersections where new timing actually went live.

    Submit this record
  • What did the City pay and recover?

    Purchase-order schedule, invoices, payment vouchers and VDOT reimbursement requests and receipts for UPC 115519. Request corresponding records under UPC 111081 if any task orders cover the same intersections.

    Likely custodian: Newport News Finance and Engineering, and VDOT

    Reconcile the tracker’s purchase-order comment and contract row, and identify which grant paid for shared work if scopes overlap.

    Submit this record
  • Did the timing changes reduce delay?

    Before-and-after corridor travel times and stop counts, intersection delay and queue measurements, pedestrian wait times and the sampling dates, time periods and traffic volumes used in the comparison.

    Likely custodian: Newport News Engineering / Traffic Operations

    Test whether changes helped travelers and whether benefits on main routes came with longer waits on side streets or crossings.